Postponement of the Core Flow-Based Market Coupling project Go Live
22.11.2021

External dependencies delayed the timely start of the first phase of Core Joint Integration Testing. In addition, technical issues encountered during the first weeks of the Joint Integration Testing, require extending the testing phase to ensure robustness of the systems.

Fixes are being prepared to commence the required re-testing. Project parties are working hard to minimise the delay.

Core project parties will inform all stakeholders on the new go live date as soon as this is aligned and confirmed by all involved parties.

For more information, please refer to the press release attached: >>