Postponement of the Core Flow-Based Market Coupling project Go Live


     

Current expectation is that the go live would take place between beginning of Q2 2022 at the earliest and before the end of Q2 2022 at the latest.

External dependencies delayed the timely start of the first phase of Core Joint Integration Testing. In addition, technical issues encountered during the first weeks of the Joint Integration Testing, require extending the testing phase to ensure robustness of the systems.

Fixes are being prepared to commence the required re-testing. Project parties are working hard to minimise the delay.

Core project parties will inform all stakeholders on the new go live date as soon as this is aligned and confirmed by all involved parties.